Small Contractor - Before Starting

30 min facilitated workshop · 4 lessons

Includes English and your selected language. Open the downloaded file in a browser to print or save as PDF. Trainer notes and marking keys are not included.

Progress and unsent notes can be resumed on this device for 30 days, separately for each language. Your name is not saved locally. Clear saved progress on shared devices. Submit sends your chosen name, exercises and answers privately with the result.

Continue learning · 0/4

Independent awareness learning for Great Britain (England, Scotland and Wales). Not HSE approved or accredited; not a regulated qualification or permission to work. Reading online does not establish practical competence or successful course completion.

Learning outcomes

  • Recognise hazards and missing information before starting.
  • Compare proposed controls with the task and actual site conditions.
  • Identify the responsible people, evidence and permissions needed.
  • Explain when to stop, report a change and obtain an authorised restart.

Course scope

Great Britain CDM awareness only. Not legal advice, principal designer qualification or approval of a real construction phase plan.

Workshop lessons

Open a lesson to read the explanation, practical example and reflection question. The first lesson is already open. Read the full text before confirming completion. Opening or closing a lesson keeps your exercise answers on this page.

01

Your role and the CPP

Open and read lesson Close lesson

Lesson explanation

CDM 2015 applies to small and domestic construction projects in Great Britain. The sole contractor or principal contractor prepares the construction phase plan before construction begins. A subcontractor working under a principal contractor contributes information and follows coordinated arrangements. Clarify the project structure; a RAMS pack does not automatically replace the CPP.

Apply this lesson to the case study before completing the worksheet. Identify what you know, what remains uncertain and who can supply reliable evidence. Record a practical action, a responsible person and a check that would show the action worked. Discuss your decision with a competent supervisor; reading and quiz completion do not authorise the work.

Key points to remember

  • CDM 2015 applies to small and domestic construction projects in Great Britain.
02

Information, access and welfare

Open and read lesson Close lesson

Lesson explanation

Before mobilisation obtain relevant information about services, asbestos, structural conditions, access and occupied areas. Agree suitable welfare, emergency arrangements and site rules. Planning should be proportionate but specific enough to guide the actual job. Record unresolved matters and who will resolve them; commercial pressure does not justify starting without necessary controls.

Apply this lesson to the case study before completing the worksheet. Identify what you know, what remains uncertain and who can supply reliable evidence. Record a practical action, a responsible person and a check that would show the action worked. Discuss your decision with a competent supervisor; reading and quiz completion do not authorise the work.

Key points to remember

  • Before mobilisation obtain relevant information about services, asbestos, structural conditions, access and occupied areas.
03

Competence and coordination

Open and read lesson Close lesson

Lesson explanation

Appoint people with suitable skills, knowledge, training and experience, or provide appropriate training and supervision while they develop them. Explain the work and check understanding in a usable language. Coordinate deliveries, other trades and shared protections. A certificate alone does not establish task competence or transfer the contractor's responsibility for planning and supervision.

Apply this lesson to the case study before completing the worksheet. Identify what you know, what remains uncertain and who can supply reliable evidence. Record a practical action, a responsible person and a check that would show the action worked. Discuss your decision with a competent supervisor; reading and quiz completion do not authorise the work.

Key points to remember

  • Appoint people with suitable skills, knowledge, training and experience, or provide appropriate training and supervision while they develop them.
04

Change, briefing and handover

Open and read lesson Close lesson

Lesson explanation

A new trade, changed sequence or unexpected condition may alter responsibilities and controls. Pause the affected work and coordinate a review with the responsible project people. Update the relevant plan and briefing before restart. At completion communicate unfinished work, remaining hazards and records needed by others. Keep the planning useful instead of copying unrelated standard text.

Apply this lesson to the case study before completing the worksheet. Identify what you know, what remains uncertain and who can supply reliable evidence. Record a practical action, a responsible person and a check that would show the action worked. Discuss your decision with a competent supervisor; reading and quiz completion do not authorise the work.

Key points to remember

  • A new trade, changed sequence or unexpected condition may alter responsibilities and controls.

Practice case

Fictional discussion exercise. This is not an approved assessment, supplier SDS, traffic plan or permit for live work.

A two-person firm is fitting a kitchen for a homeowner. The client may appoint an electrician separately. The crew has generic RAMS but no confirmed construction phase plan, welfare arrangement or coordination contact. The start date is tomorrow.

Your tasks

  1. List the missing information and identify what prevents a safe start.
  2. Choose suitable controls and name who must verify them.
  3. Explain your stop decision, escalation route and restart conditions.
  4. Brief the team and ask them to explain the controls in their own words.
Information still missing
Decision before starting or continuing

Planning worksheet

Do not invent missing technical specifications. Record uncertainty and identify the competent person or authorised role needed to resolve it.

Issue or work stage
Control or information needed
Owner and check
Issue or work stage
Control or information needed
Owner and check
Issue or work stage
Control or information needed
Owner and check
Issue or work stage
Control or information needed
Owner and check
Issue or work stage
Control or information needed
Owner and check
Pause and restart arrangements

Workplace action and feedback

One change I will make
Who must help or authorise the change
Target date and supervisor contact
How we will check the change works
Further instruction or practical training needed
What is clearer now? What remains unclear? Were the language, pace and format suitable?

Official HSE sources (English)

Source check: 6 November 2026. Review current guidance and actual site procedures before use. Northern Ireland and other jurisdictions need separate review.

Version 2.0 · Learner edition · SHEQ Excellence Group Ltd

Automatic knowledge check

Mark every lesson as read, complete the case, at least the first planning row and your action plan, then answer all eight questions. Required notes: missing information, decision, pause/restart, improvement, helper, target date and effectiveness check. Remaining rows, further-training needs and feedback are optional.

Pass: at least 6/8 (75%) with both questions marked safety-critical correct. These are SHEQ course rules, not HSE pass marks. Practical notes are saved but not automatically marked.

Eight questions are selected from a twelve-question bank. Both safety-critical questions are always included; question and answer order can change. The pass rule remains 6/8 with both critical answers correct.

A participation certificate is issued after every complete, marked submission. It states the score and pass/not-passed status. A failed test requires further study and a new attempt.

Lessons marked as read: 0/4

Automatic knowledge check
1. The sole contractor has generic RAMS but no CPP. May construction start on that basis? Safety-critical
2. A worker is still learning the assigned task. What must be arranged? Safety-critical
3. You are a subcontractor under an appointed principal contractor. Who prepares the project CPP?
4. The client appoints another trade after the plan is agreed. What should happen?
5. Conditions differ from the plan when the crew arrives. What should happen?
6. A worker cannot explain an important control after the briefing. What next?
7. The client offers a generic RAMS pack for a different site. How should it be used?
8. Does completing this workshop authorise a specialist task?

Submitting sends your name, answers, practical notes, lesson declarations, result, course version, language and date to SHEQ for a private training record. A necessary secure cookie protects access. Records expire after 12 months and are removed on subsequent service use; download your certificate now and keep the cookie to re-download. Identity is self-declared. For access or deletion contact sheqexcellencegroup@gmail.com.